Changes to Planning Enforcement Time Limits
New planning enforcement time limits came into force from 25 April 2024 (subject to transitional arrangements). The changes will have significant implications for those affected by them.
Planning enforcement summary
A breach of planning control is defined in section 171A of the Town and Country Planning Act 1990 (TCPA) as:
- the carrying out of development without the required planning permission; or
- failing to comply with any condition or limitation subject to which planning permission has been granted.
Local planning authorities have responsibility for taking whatever enforcement action may be necessary and in the public interest. There is a range of ways of tackling alleged breaches of planning control, and local planning authorities should act in a proportionate way.
However, prior to 25 April 2024, section 171B TCPA provided that in most cases, development becomes immune from enforcement following a period of either four or 10 years, depending on the type of breach.
Four-year enforcement period
Under the old regime, breaches of planning control which consisted of the carrying out without planning permission of building, engineering, mining or other operations in, on, over or under land were immune from enforcement after four years from the date on which the operations were substantially completed. This wide definition included operational development not permitted by a planning permission. The four-year rule also applied where there had been breaches of planning control consisting of a change of use of a building to use as a single dwelling house.
New planning enforcement time limits
Section 115 of the Levelling Up and Regeneration Act 2023 (LURA) has changed the period for all breaches of planning control to 10 years. The change will only apply to England, not Wales. However, there are transitional provisions.
Transitional provisions
The transitional provisions provide that where operations under Section 171B (1) TPCA were substantially complete or a change of use to a single dwellinghouse occurred before the 25 April 2024, the four year period will continue to apply.
However, where there has been concealment of a breach, the local authority still has the right to take enforcement action out of time.
Comment
It is possible to apply under Section 191 TCPA to establish whether a breach of planning control has become lawful due to passage of time, and this will be determined on the balance of probabilities. Evidence will be needed in the form of things like invoices, receipts, photographs, etc. demonstrating when works were carried out.
For those affected or potentially affected by the new provisions, it will be important to ask the developer / vendor to provide evidence that any unlawful building operations and/or change of use to a dwelling house were substantially completed prior to 25 April 2024. It will also be important to take professional advice at the earliest opportunity on whether the evidence produced is sufficient evidence to justify a finding that the four-year period applies.
If an enforcement notice is served after the lapse of the relevant time limit, it is possible to appeal. Any appeal must be submitted before the date the Enforcement Notice takes effect, and that deadline cannot be extended.
If you have any concerns about planning permission breaches and planning enforcement time limits, please get in touch.
The legal content provided by RSW Law Limited is for information purposes only and should not be relied on in any specific case without legal or other professional advice.
Copyright is owned by RSW Law Limited and all rights in such copyright are reserved. Material is not to be reproduced in whole or in part without prior written consent.